

 |
 |
Don’t Forget the Site in LEED Certification

You are considering making the commitment to make
your next project a LEED certified project.
What does it really mean for you, for the contractor
and for the design team? Beyond the obvious, widely
marketed bragging-rights, is a very stringent list
of prerequisites that will have major impact on how
your project is designed and developed.
Each site is very different with regard to location,
size, access routes, construction material storage
areas, and topography. All of these influence how the
project will be developed. A recent project of Ecos’ that
met the criteria for LEED certification is a good example
of the unique characteristics that might exist on a
site. The Klaus Advanced Computing Building, located
in the heart of the Georgia Institute of Technology’s
campus, was an extremely challenging site for both
the designers and the general contractor to work with,
due to the compact site envelope and extreme grade
change. To further complicate matters, it involved
working within an active college campus.
If you have the luxury of selecting your project site,
the following LEED prerequisites will limit your search
to sites that
- Are not
considered prime farmland (as defined by the US Department
of Agriculture).
- Have an
elevation that is 5 feet above the 100-year FEMA
flood limit.
- Have not
been identified as a habitat for any species on
Federal or State threatened or endangered lists.
- Are not
within 100 feet of any water (including wetlands).
- Were not
formerly public parkland.
- Are on or
near public transportation.
The overall intent of these requirements is to discourage
development of sites that will suffer undue environmental
impact.
|
 |
|
 |
|
As the design concept is further developed, the impact
of the reduced site disturbance credit will continue
to influence other design elements such as stormwater
management. LEED provides an opportunity to achieve
compliance through rate and quantity as well as treatment.
Depending on the amount of existing imperviousness
of the site, compliance could require as much as a
25% reduction in both the rate and quantity of stormwater
runoff. The possible footprint for this amount of reduction
could be significant, especially if the project is
trying to limit the amount of site disturbance. Careful
planning and design will be important to ensure compliance
for each of the credits.
This creative design approach is reflected in the
Klaus Building’s stormwater management system,
which includes 170,000 gallons of below-grade cistern
storage, skillfully integrated within the site, just
adjacent to the building’s face, to limit the
amount of site disturbance.
Additional levels of coordination with the general
contractor were required since the same real estate
needed to permit construction equipment, scaffolding,
and utilities, needed to remain permeable for stormwater
infiltration. The Klaus project achieved this balance
through a multi-stage design approach that permitted
the contractor to “back out” of the area.
Complex designs as well as high expectations for site
construction techniques are only achievable through
experience and good communications. Employing LEED-experienced
design professionals, as well as general contractors,
and initiating the dialog between the two groups during
the design process can save the project not only money,
but could ultimately be the critical step in achieving
design elements as well as LEED credits.
|
 |
|
|
 |